These are the Hanger updates for Sept. 2005
Sept 21st, 2005 Update.... Interior walls sheetrocked, electrical in, roof/ceiling
trusses installed.
 
Left, Bill Golding and B.J. Waters putting up more sheetrock. The kitchen
is sheetrocking finished.
Right, The ceiling joists here are 16" BCI laminated trusses placed 16"
on Center.
These allow for the 25' wide open span and will provide structural strength
for storage or office space above.
The restrooms are also framed in and wiring and plumbing is installed.
Joe Neemer and his crew have checked all the electrical and the McGregor building
inspector says "cover it up".
We still need 12 more ceiling trusses and loads of sheetrock, ceiling lights
and several other things.
If any of you "Deep-Pockets" out there are willing, now is the time
to step up. We're almost finished but still need about $5,000 for completion.
So far all this work and expenses have been paid by the chapter membership.
If you're interested in making a donation here is a like to more
information. And remember your donations are tax deductable.
Photos compliments Emmette Craver.
Sept. 11th, & 21st, 2005. Update... Interior walls
and partitions being built.
 
Partitions for the kitchen, restrooms, and conference room.
Later when the second phase #2 section is constructed we will move the conference
room to that area.
This temporary conference room area will then be available as a climate controlled
work area.
   
|